What are the various formulas for ETC?

Wednesday, November 2, 2011

• ETC = EAC-AC: Use formula when no keywords (i.e. typical, atypical or flawed) are given.
• ETC = BAC-EV: Assumption: use formula if current variances are thought to be atypical in the future.
• ETC = (BAC-EV) / CPI: Assumption: use formula if current variances are thought to be typical in the future.
• ETC = New estimate when it is thought that the original estimate was flawed.

www.codecollege.NET|www.interviewsguru.com|The Encylopedia of Web Sites|Blogging and Earning

What is the formula for Present Value in project management ?

Thursday, October 6, 2011

PV = Future Value / (1 + I)^n where I is the interest rate and n is the number of periods.

www.codecollege.NET|www.interviewsguru.com|The Encylopedia of Web Sites|Blogging and Earning

What is the formula for Future Value in project management ?

FV = Current Value x (1 + I)^n where I is the interest rate and n is the number of periods.

www.codecollege.NET|www.interviewsguru.com|The Encylopedia of Web Sites|Blogging and Earning

What is the formula for ROI in project Management ?

ROI = (Benefit – Cost)/Cost